Landlord EICR rules in England: a plain guide
By Liam, OHMS GROUP LTD ·
If you let a home in England, the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020 require the fixed electrical installation to be inspected and tested by a qualified person at least every five years. The result is an Electrical Installation Condition Report, and the regulations set clear deadlines for sharing it and for fixing anything it finds.
Since 2025 the same rules have been extended to social housing, so housing associations and councils are now covered too.
How often the installation must be tested
The installation must be inspected and tested at intervals of no more than five years, or sooner if the last report says so. Inspectors sometimes recommend a shorter interval for an older installation, and that earlier date then becomes the deadline. Make sure a valid report is in place before a new tenancy begins, because the new tenant must be given a copy before they move in.
Who must get a copy, and when
- Each existing tenant: within 28 days of the inspection
- A new tenant: before they move in
- A prospective tenant: within 28 days of asking in writing
- The local housing authority: within 7 days of a written request
- The electrician carrying out the next inspection
Keep a copy until the next inspection is done. Your letting agent may handle the paperwork, but the legal duty stays with you as the landlord.
When the report is unsatisfactory
If the report shows the installation does not meet the standards, with C1 or C2 observations, or says further investigation is needed, the work must be carried out by a qualified person within 28 days of the inspection, or sooner if the report says so. Our guide to EICR codes explains what each code means.
Once the work is done you must get written confirmation from the electrician that it is complete and the standards are met, or that more work is needed. That confirmation, together with the original report, must go to each tenant and to the local authority within 28 days of the work being completed.
C3 items are recommendations. They do not have to be fixed to comply, though they are often worth doing while an electrician is on site.
Social housing: the new dates
The rules were extended to the social rented sector by amending regulations in 2025. They apply to social tenancies granted from 1 December 2025, and to existing social tenancies from 1 May 2026, with the first checks on existing homes due to be completed by 1 November 2026. Social landlords must also have any electrical appliances they provide, such as cookers or white goods, inspected or tested at least every five years.
If you manage social homes and still have properties without a current report, the November deadline is close.
Penalties
Local authorities enforce the regulations. Where a landlord is in breach they can serve a remedial notice, arrange the work themselves and recover the cost, and impose a financial penalty of up to £30,000.
Practical tips for landlords
- Keep a simple record of each property's last EICR date and next due date
- Book the next inspection a couple of months early so there is time for any remedial work
- Give tenants plenty of notice. Testing means turning the power off in stages
- Ask for remedial work to be quoted separately, so you can compare prices
- Check smoke and carbon monoxide alarms on the same visit, since those have their own legal rules
What the regulations do not cover
The 2020 regulations are about the fixed installation: the wiring, consumer unit, sockets, switches and fixed appliances such as electric showers. Private landlords are not required by these regulations to test appliances they supply, such as a cooker or washing machine, although those still have to be safe. Many landlords have supplied appliances checked at the same visit, which also gives a useful record if a tenant reports a fault. Tenants' own appliances are their responsibility.
Gas safety, and smoke and carbon monoxide alarms, are covered by separate rules with their own deadlines, so keep each set of records separate and up to date.
Is the electrician qualified?
The regulations require a qualified person, meaning someone competent to inspect and test to BS 7671. Ask what experience they have with periodic inspection, and make sure the report includes a full schedule of test results, not just a single page certificate.
Landlord EICRs in Maidstone, Medway and Tonbridge
We work around tenants, provide the report promptly, explain each observation and can carry out remedial work within the 28-day window. See our landlord EICR and testing service and, where a board needs replacing, our consumer unit upgrades. We cover Maidstone, Medway and Tonbridge. Call 01622 278762 to book.
Common questions
How often do landlords need an EICR in England?
At least every five years, or sooner if the previous report recommends an earlier date, and before a new tenancy if there is no valid report.
How long do I have to fix faults on a landlord EICR?
28 days from the inspection, or less if the report specifies. You then have 28 days from completion to send written confirmation to tenants and the council.
Do the rules apply to social housing?
Yes. They apply to new social tenancies from 1 December 2025 and existing ones from 1 May 2026, with first checks due by 1 November 2026.