Emergency lighting testing: monthly and annual checks

By Liam, OHMS GROUP LTD ·

Emergency lighting comes on when the normal lighting fails, so people can find their way out safely. In most commercial buildings it is part of the fire safety arrangements your fire risk assessment relies on. Like a fire alarm, it is only useful if it works on the day, and the code of practice, BS 5266-1, sets out how it should be tested.

With the clocks gone back and longer dark evenings, winter is when a failed emergency light is most likely to matter.

Who is responsible

Under the Regulatory Reform (Fire Safety) Order 2005, the responsible person, usually the employer, owner or managing agent, must make sure fire safety measures, including emergency lighting, are maintained in working order. Staff or a contractor can carry out the tests, but the responsibility stays with the responsible person.

The types of emergency lighting

  • Escape route lighting, so corridors, stairs and exits can be seen and followed
  • Open area lighting, sometimes called anti-panic lighting, for larger spaces where people need to reach an escape route
  • High risk task area lighting, so a dangerous process or machine can be shut down safely

Fittings are either maintained, meaning they are lit all the time and stay on when the power fails, or non-maintained, meaning they only light when the normal supply is lost. Exit signs over doors are often maintained.

The monthly function test

Once a month each emergency light should be tested by briefly simulating a failure of the normal supply, usually with a key switch fitted near the lighting circuit. Every fitting should light. This is often called the flick test because it only takes a short time.

Walk the whole building while the test is on, including stairwells, plant rooms and toilets, and note any fitting that does not light, flickers or is visibly damaged.

The annual full duration test

Once a year each fitting should be run on its battery for its full rated duration, which is commonly three hours. Any fitting that does not stay lit for the whole period has a battery or lamp that needs replacing.

After a full duration test the batteries need time to recharge, and during that time the building has reduced cover. For that reason annual tests are usually done when the building is empty or lightly used, such as at the end of the day, at a weekend, or by testing alternate fittings on different days.

The logbook

Every test should be recorded. A typical entry includes:

  • The date and the type of test
  • Which fittings were tested and the results
  • Any faults found and what was done about them
  • The name of the person who carried out the test

Fire risk assessors and the fire service will ask to see the logbook. A missing or blank logbook is treated the same as a system that has not been tested.

Self-test fittings

Self-test emergency lights run their own monthly and annual tests and show a status light or report to a central panel. They save time in larger buildings, but someone still needs to check the indicators, act on faults and keep records.

New systems and alterations

A new emergency lighting system should be designed to BS 5266-1 for the way the building is used, then commissioned and handed over with certificates and a logbook. Whenever rooms are partitioned, walls move or a space changes use, check that routes, exits and open areas still have cover. Office fit-outs are the most common reason an older system stops matching the building.

Common faults we find

  • Batteries that no longer last the full rated duration
  • Fittings fed from a different circuit to the test switch, so the monthly test never actually tested them
  • Areas added or rearranged since the original design, leaving routes or new rooms without cover
  • Missing or illegible exit signs

Emergency lighting and fire alarms together

Emergency lighting, fire detection and clear escape routes all come from the same fire risk assessment. If you are reviewing one, it makes sense to look at the others. Our guide to fire alarm categories explains how the alarm side is specified.

Emergency lighting testing in Kent and London

We carry out monthly and annual emergency lighting tests, keep your logbook up to date and repair or replace failed fittings. See our electrical testing service, which includes emergency lighting, and our fire alarm installation and maintenance. We work across Maidstone, the rest of Kent and London. Call 01622 278762 to arrange testing.

Common questions

How often should emergency lighting be tested?

BS 5266-1 recommends a short function test every month and a full rated duration test, commonly three hours, once a year, with results logged.

Can my own staff do the monthly test?

Yes, if they are shown how. The responsible person must make sure it is done and recorded, and act on any faults.

What happens after the annual test?

Batteries need time to recharge, so cover is reduced. Plan annual tests for quiet periods or test alternate fittings on different days.